Nicholson/Pennsylvania Project Update: Widened Road Expected To Reopen In Mid-October

A widened Nicholson/Pennsylvania is expected to reopen in mid-October.

That’s according to an update provided by our city engineer at Tuesday’s Public Works & Public Property Committee meeting.

The storm sewers are in, as is the retention pond, and rough grading is now complete. Still to go are curb, gutter, asphalt binder, sidewalk/concrete driveways, topsoil/lawns, asphalt surface, asphalt driveways and, finally, pavement marking.

I’ll keep you posted on the project, which will see the stretch of Nicholson/Pennsylvania between College and Rawson Avenues widened to four lanes.

Check out a previous post on the project here.

Leave a Comment

Filed under Construction, Transportation

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s