Just three more months to go …
The ongoing improvements to 15th Avenue between College and Rawson Avenues will be complete by August 30. That’s according to a letter sent to area property owners this week by City Engineer Kyle Vandercar.
Three phases are planned:
- May 20 to June 11: North of Oak Creek Parkway to College Avenue
- June 14 to July 11: Intersection of 15th Avenue and Oak Creek Parkway
- July 25 to August 30: North of Rawson to Oak Creek Parkway
Of course, the plans may change due to weather, change orders or other circumstances, but this is good news because it means work should be done in time for the start of the 2010-11 school year.
Keep in mind that connecting streets will be closed during construction phases, and traffic will need to use other routes. Please be patient during this time … and keep your eye on the prize (a great new road through the 4th District).
If you have any additional 15th Avenue construction questions, contact Chad Bigler at OTIE at 414-856-1345. You may also reach Kyle at 414-762-2222, ext. 136.