Parkway Drive/17th Avenue Construction Update

Work on Parkway Drive and 17th Avenue will take a little longer than expected.

Here is the most recent update being mailed to area residents. Among the highlights:

  • Pavement, removal and grading will continue north the week of May 21, and additional segments may be paved; but we anticipate gravel surface from Pine to Hemlock through the Memorial Day weekend.
  • Sanitary sewer, storm sewer, and watermain repairs/upgrades on the northerly portion of the job have taken longer than anticipated, but we expect the entire project to be substantially complete by mid-June.

Your patience is appreciated. I’ll keep you posted.