Nicholson/Pennsylvania Project Update: Widened Road Expected To Reopen In Mid-October

A widened Nicholson/Pennsylvania is expected to reopen in mid-October.

That’s according to an update provided by our city engineer at Tuesday’s Public Works & Public Property Committee meeting.

The storm sewers are in, as is the retention pond, and rough grading is now complete. Still to go are curb, gutter, asphalt binder, sidewalk/concrete driveways, topsoil/lawns, asphalt surface, asphalt driveways and, finally, pavement marking.

I’ll keep you posted on the project, which will see the stretch of Nicholson/Pennsylvania between College and Rawson Avenues widened to four lanes.

Check out a previous post on the project here.

Leave a comment

Filed under Construction, Transportation

Get Ready: Pennsylvania/Nicholson Project Starts June 26

The long-planned widening of Pennsylvania/Nicholson Avenue between College and Rawson Avenues begins on June 26.

That means the road will be closed to through traffic starting at that point … so please plan an alternate route.

Construction will last until early October.

Learn more in this letter sent to area residents and in this Oak Creek Patch story.

I’ll keep you posted … and, as always, thanks for your patience during the construction.